How to Calculate Manufacturing Cost Per Unit, Including Wastage and Labour

27 November 2026 21 min read

Operator at a CNC machine control panel

Manufacturing cost per unit tells you how much it really costs to produce a saleable product. To calculate it accurately, you need to consider raw materials, normal wastage, direct labour and production overheads—not just the purchase price of the materials.

For a manufacturer, knowing the actual cost of production is essential for setting selling prices, preparing quotations, evaluating product profitability and controlling expenses.

A product that appears profitable based on raw material cost alone may generate a much smaller margin after labour, machine time, electricity, factory overheads and production losses are included.

The challenge is that these costs may be recorded in different places. Material consumption is recorded by the warehouse, labour hours by production supervisors, machine usage by operations teams and indirect expenses by finance. Unless these figures are brought together, the business may not know the true cost of a finished unit.

This guide explains how to calculate manufacturing cost per unit, account for wastage and labour, allocate production overheads and use ERPNext to improve production cost visibility.

The basic principle: Calculate the cost of the materials and resources consumed in production, then divide the appropriate production cost by the number of good units completed—not simply by the quantity originally planned.

1. What Is Manufacturing Cost Per Unit?

Manufacturing cost per unit is the cost of converting raw materials and other production resources into one finished unit.

It includes the costs that are directly related to production and an appropriate allocation of manufacturing overheads.

The main components are:

1. Direct materials

These are the raw materials and components that become part of the finished product or are directly consumed during manufacturing.

Examples include:

  • Steel, aluminium and sheet metal.
  • Plastic granules and resins.
  • Wood, boards and fittings.
  • Electronic components.
  • Packaging materials used as part of the finished product.
  • Other components listed in the Bill of Materials.

2. Direct labour

Direct labour is the cost of employees who work directly on manufacturing the product or performing identifiable production operations.

Examples include:

  • Machine operators.
  • Assembly workers.
  • Fabricators and welders.
  • Production technicians.
  • Employees performing product-specific finishing or processing.

3. Manufacturing overheads

These are indirect production costs that support the manufacturing process but cannot always be traced economically to an individual unit.

Examples include:

  • Factory electricity and utilities.
  • Machine depreciation.
  • Equipment maintenance.
  • Factory rent where attributable to production.
  • Production supervision.
  • Indirect production labour.
  • Factory consumables and supporting materials.

4. Normal production wastage

Materials may be lost during cutting, machining, mixing, finishing, assembly or other production operations. Where a normal level of wastage is expected in the production process, the material requirement and cost per good unit should reflect that expected yield.

However, abnormal waste, avoidable damage and unusual production losses should be identified separately. They should not automatically be absorbed into the cost of every good unit.

2. The Manufacturing Cost Per Unit Formula

The basic formula is:

Total Manufacturing Cost = Direct Material Cost + Direct Labour Cost + Allocated Manufacturing Overheads

The cost per saleable unit is then:

Manufacturing Cost Per Unit = Total Manufacturing Cost ÷ Good Units Produced

Where recoverable scrap or by-products have a measurable value, their treatment should follow the company's costing policy and applicable accounting requirements. Do not deduct scrap value automatically without considering how it is recorded.

What should be included?

Cost ComponentExamplesCalculation Basis
Direct materialsRaw materials and componentsQuantity consumed × applicable material rate
Direct labourProduction workers and operatorsProduction hours × loaded hourly labour rate
Variable overheadProduction utilities and consumablesActual usage or an appropriate activity rate
Fixed production overheadFactory depreciation, production rent and supervisionSystematic allocation based on normal production capacity
Normal process wastageExpected material loss during productionReflected in material requirements and good-unit yield

Under IAS 2, inventory cost includes purchase costs, conversion costs such as direct labour and production overhead, and other qualifying costs incurred to bring inventory to its present location and condition. The standard also distinguishes abnormal waste and certain other costs that should be recognised as expenses rather than included in inventory cost.

3. How to Calculate Direct Material Cost

Direct material cost is usually the starting point for manufacturing costing. The business needs to know how much material is required for the finished product and what that material actually costs.

Step 1: Identify the materials required

Prepare a Bill of Materials (BOM) for the finished product. It should identify each raw material or component, its required quantity and the relevant unit of measure.

For example, manufacturing one metal enclosure may require:

MaterialQuantity Per UnitRate (AED)Cost Per Unit (AED)
Steel sheet2 kg12.00 per kg24.00
Fasteners8 pieces0.50 per piece4.00
Protective coating0.2 litre15.00 per litre3.00
Total31.00

The material cost for one unit is AED 31 before considering additional process loss or wastage.

Step 2: Use the appropriate material rate

The rate should reflect the company's chosen costing method and the cost of the material available for production.

Depending on the business and inventory valuation policy, the rate may be based on:

  • FIFO valuation.
  • Moving Average valuation.
  • Standard cost.
  • Another permitted costing technique that appropriately approximates cost.

The business should use a consistent approach and ensure that material rates reflect relevant purchase costs, non-recoverable duties and directly attributable costs where applicable.

Step 3: Calculate the actual material consumed

Do not rely only on the quantity specified in the BOM. Compare the planned material requirement with the quantity actually issued or consumed.

For example:

  • Planned material requirement: 100 kg.
  • Actual material issued: 110 kg.
  • Good production output: 100 units.

The difference should be investigated and classified. It may represent expected process loss, additional usage, rework, damage or an operational error.

4. How to Include Material Wastage and Rejects

Wastage is one of the most frequently overlooked parts of manufacturing cost calculation.

A BOM may show that one unit requires a specific quantity of material, but actual production may consume more because of cutting loss, trimming, evaporation, rejected components or other process-related losses.

Understand the different types of production loss

TypeMeaningCost Treatment Consideration
Normal wastageExpected material loss under normal operating conditions.Normally reflected in the planned material consumption and cost of good output.
Abnormal wastageUnusual or avoidable loss beyond normal production expectations.Identify separately; under IAS 2, abnormal wasted materials, labour and other production costs are excluded from inventory cost.
ReworkAdditional work required to bring a product within specification.Record the additional material and labour; assess whether it is normal or abnormal.
Rejected productionUnits that fail inspection and cannot be sold as intended.Record rejected quantity and investigate whether the loss is normal or abnormal.
Recoverable scrapResidual material that can be sold or reused.Record its quantity and value using the company's approved costing policy.

How to calculate the wastage rate

A simple material wastage calculation is:

Wastage Rate (%) = Wasted Material Quantity ÷ Total Material Input × 100

For example, if a production batch uses 110 kg of material and 10 kg is recorded as normal process loss:

Wastage rate = 10 ÷ 110 × 100 = 9.09%

The remaining 100 kg is represented in the finished output in this simplified example.

How to calculate material cost including wastage

Suppose the material rate is AED 20 per kg and the production batch consumes 110 kg.

DescriptionQuantityRateCost
Total material input110 kgAED 20/kgAED 2,200
Normal process loss10 kgAED 20/kgAED 200
Material represented in good output100 kgAED 20/kgAED 2,000

If the batch produces 100 good units, the material cost allocated to each good unit is:

AED 2,200 ÷ 100 good units = AED 22 per unit

Without accounting for wastage, the business might calculate the material cost as AED 20 per unit. That would understate the material cost by AED 2 per good unit in this example.

How to calculate material required when wastage is a percentage

If the normal wastage rate is expressed as a percentage of total input, the required input can be estimated using:

Required Material Input = Required Good Output ÷ (1 − Wastage Rate)

For example, if the target is 100 kg of usable output and the normal wastage rate is 5% of total input:

Required input = 100 ÷ 0.95 = 105.26 kg.

This calculation is useful for estimating procurement and BOM quantities. Actual production results should still be recorded and compared with the planned yield.

Do not hide abnormal wastage in unit cost

Suppose a machine breakdown damages an unusually large quantity of material. If the additional loss is simply included in the cost of all good units, the reported product cost may become misleading.

Under IAS 2, abnormal amounts of wasted materials, labour and other production costs are excluded from inventory cost and recognised as an expense in the period incurred. Businesses should document their normal yield assumptions and investigate significant deviations.

5. How to Calculate Direct Labour Cost

Labour is another important part of manufacturing cost. A product may use relatively inexpensive materials but require considerable skilled labour, assembly time or machine operation.

Step 1: Identify the production activities

List the operations required to manufacture the product.

For example:

  • Cutting.
  • Drilling.
  • Welding.
  • Assembly.
  • Finishing.
  • Quality inspection.

Step 2: Calculate the labour hours

Record the time employees spend performing the relevant production operations.

The time may be captured using Job Cards, timesheets, production logs or another approved method.

Step 3: Calculate the loaded hourly labour rate

The hourly labour rate should reflect the labour costs attributable to the employee or production activity, not necessarily just the basic salary.

Depending on the company's costing policy, it may include:

  • Basic wages or salary.
  • Applicable allowances.
  • Employer-paid benefits and employment costs.
  • Other directly attributable labour costs.

The business should define which costs are included and use a consistent calculation.

Hourly Labour Cost = Relevant Labour Cost for the Period ÷ Productive Labour Hours

Worked labour example

A production worker has an attributable monthly labour cost of AED 6,000 and 200 productive hours in the month.

Hourly labour rate = AED 6,000 ÷ 200 = AED 30 per hour.

If a batch requires 40 direct labour hours:

Direct Labour Cost = 40 hours × AED 30 = AED 1,200

If the batch produces 100 good units:

Labour Cost Per Unit = AED 1,200 ÷ 100 = AED 12

Why actual labour time matters

A standard BOM may estimate that a product takes 20 minutes to assemble. Actual production may take 30 minutes because of rework, machine waiting time, material handling or operator inefficiency.

Comparing planned and actual labour hours helps identify:

  • Operations taking longer than expected.
  • Training or skill gaps.
  • Production bottlenecks.
  • Excessive rework.
  • Incorrect standard operation times.
  • Opportunities to improve production methods.

6. How to Calculate Manufacturing Overheads

Manufacturing overheads are the indirect costs required to operate the factory. They need to be allocated to production using a rational and consistent method.

Common manufacturing overheads

Overhead CategoryExamples
Factory facilitiesProduction-related rent and facility expenses.
Machine costsDepreciation, maintenance and servicing.
UtilitiesElectricity, water and production-related utilities.
Indirect labourProduction supervisors and support staff.
Factory consumablesLubricants, cleaning supplies and indirect materials.
Quality controlProduction inspection and testing resources.

Method 1: Machine-hour rate

For machine-intensive production, overhead can be allocated based on machine hours.

Machine-Hour Rate = Allocatable Machine Overhead ÷ Normal or Planned Machine Hours

If the monthly allocatable machine overhead is AED 10,000 and the relevant normal production capacity is 400 machine hours:

Machine-hour rate = AED 10,000 ÷ 400 = AED 25 per machine hour.

A product requiring 20 machine hours would receive an overhead allocation of AED 500 using this rate.

Method 2: Direct labour-hour rate

For labour-intensive production, overhead can be allocated based on direct labour hours.

Labour-Hour Overhead Rate = Allocatable Production Overhead ÷ Normal Direct Labour Hours

If allocatable production overhead is AED 12,000 and normal direct labour capacity is 600 hours:

Overhead rate = AED 12,000 ÷ 600 = AED 20 per labour hour.

Method 3: Production unit or batch rate

For highly standardised production, a business may use an appropriate rate per unit or per batch, provided it reasonably reflects how production resources are consumed.

The chosen allocation basis should reflect the actual production environment. A single rate for all products may be unsuitable when products use very different machines, labour hours or production processes.

Fixed overhead and normal capacity

Fixed production overhead should be allocated systematically based on the normal capacity of the production facilities. A period of unusually low production should not automatically increase the overhead absorbed into each unit. Unallocated fixed overhead arising from low production is generally recognised as an expense for the period under IAS 2.

This distinction is important when comparing product costs across months with different production volumes.

7. Worked Example: Calculating Manufacturing Cost Per Unit

Consider a manufacturer producing 100 metal components in one production batch.

The following figures are illustrative and assume that the recorded material loss is normal process wastage.

Production details

  • Good finished units: 100.
  • Raw material consumed: 110 kg.
  • Material rate: AED 20 per kg.
  • Normal process loss: 10 kg.
  • Direct labour hours: 40.
  • Loaded labour rate: AED 30 per hour.
  • Machine hours: 20.
  • Machine overhead rate: AED 25 per hour.
  • Other allocated production overhead: AED 300.

Step 1: Calculate material cost

110 kg × AED 20 = AED 2,200.

Step 2: Calculate labour cost

40 hours × AED 30 = AED 1,200.

Step 3: Calculate machine overhead

20 machine hours × AED 25 = AED 500.

Step 4: Add other production overhead

Other allocated production overhead = AED 300.

Step 5: Calculate total manufacturing cost

Cost ComponentTotal Cost (AED)Cost Per Good Unit (AED)
Direct materials, including normal wastage2,20022.00
Direct labour1,20012.00
Machine overhead5005.00
Other production overhead3003.00
Total4,20042.00

Result: Manufacturing cost per good unit = AED 42.00.

The total batch cost is AED 4,200 and the batch produces 100 good units.

AED 4,200 ÷ 100 good units = AED 42 per unit

What if wastage is ignored?

If the manufacturer assumes that only 100 kg of material was required, the material cost would be AED 2,000 rather than AED 2,200.

The total calculated production cost would then be AED 4,000, giving a unit cost of AED 40.

The difference is AED 2 per unit. Across repeated production batches, this difference can materially affect quotation accuracy and product profitability.

8. How Manufacturing Cost Affects Selling Price and Margin

Once the cost per unit is calculated, the business can use it as an input when setting selling prices.

However, manufacturing cost is not automatically the same as the final selling price. The company may also need to consider distribution, sales, administration, financing, warranty, risk and its target profit margin.

Example: Adding a target gross margin

Suppose the manufacturing cost per unit is AED 42 and the business wants a 30% gross margin on the selling price.

Selling Price = Cost Per Unit ÷ (1 − Target Gross Margin)

Selling price = AED 42 ÷ 0.70 = AED 60.

At a selling price of AED 60:

  • Manufacturing cost: AED 42.
  • Gross profit before other expenses: AED 18.
  • Gross margin: 30%.

A 30% markup is not the same as a 30% gross margin. A 30% markup on AED 42 would produce a selling price of AED 54.60, which gives a gross margin of approximately 23.1%.

The business should decide whether its pricing target is based on markup, gross margin or a broader contribution and profitability calculation.

Review profitability by product

Two products may have similar selling prices but very different manufacturing costs.

A product requiring more machine time, skilled labour, material processing or quality inspection may have a lower margin than expected.

Reviewing cost by Item, production batch and product family helps management identify:

  • Products with consistently low margins.
  • Materials contributing most to production cost.
  • Operations consuming more labour than planned.
  • Products with high wastage or rejection rates.
  • Manufacturing processes that need redesign or improvement.

9. Calculating and Tracking Manufacturing Costs in ERPNext

ERPNext provides manufacturing records that can help businesses calculate planned production costs and capture actual material and operation costs.

The key records include Bills of Materials, Operations, Workstations, Routing, Work Orders, Job Cards and Stock Entries. Together, they help connect product structure, production activity, material consumption and manufacturing output.

1. Bill of Materials: Define the expected product cost

The Bill of Materials (BOM) lists the raw materials, components and operations required to manufacture an Item.

ERPNext BOM costing can use material valuation rates and operation costs to calculate an estimated manufacturing cost. The BOM can also include expected scrap or process loss information, depending on the version and configured workflow.

A correct BOM is essential for reliable material planning and planned product costing.

2. Operations and Workstations: Define production activities

Operations describe the steps involved in manufacturing. Workstations represent the locations or equipment where those operations are performed.

The operation and routing setup can include:

  • Operation name.
  • Default workstation.
  • Operation time.
  • Hourly operating rate.
  • Batch size.

These details help calculate planned operating costs and provide a basis for comparing planned and actual production performance.

3. Work Order: Plan and control the production batch

A Work Order records the Item to be manufactured, quantity, BOM and production requirements.

ERPNext can show planned operating costs based on BOM operations and actual operating costs based on Job Card activity. Additional operating costs can also be recorded where applicable.

4. Job Cards: Capture actual operation time and cost

Job Cards can be used to track production operations and their execution.

The actual operation time and actual operating cost can be updated through Job Card activity. This allows the business to compare the planned time and cost with what happened on the production floor.

5. Stock Entries: Record material consumption and finished output

Stock Entries record the movement of raw materials into Work-in-Progress and the completion of finished goods.

The business should ensure that material consumption reflects actual production activity. If actual material usage differs from the BOM, the reason should be recorded and reviewed.

6. Scrap and process loss: Record production yield

ERPNext supports scrap and process-loss recording in relevant manufacturing workflows. Scrap Items can be recorded as output, while process loss can reduce the finished quantity produced.

For ERPNext Version 16, the BOM Scrap Items table has been replaced by Secondary Items, which supports additional output types such as co-products, by-products and additional finished goods. The available behaviour depends on the installed version.

7. Compare planned cost with actual cost

A useful manufacturing costing process should compare:

  • Planned material quantity versus actual material consumption.
  • Planned material cost versus actual material cost.
  • Planned operation time versus actual operation time.
  • Planned operating cost versus actual operating cost.
  • Planned production quantity versus good finished quantity.
  • Expected process loss versus actual process loss.

This comparison helps identify where cost differences arise and whether they are caused by purchasing prices, material usage, labour time, machine utilisation or production yield.

Implementation note: ERPNext provides the underlying BOM, Work Order, Job Card, Stock Entry and scrap/process-loss records. A complete cost-per-saleable-unit report that combines actual material cost, labour, overhead allocation, good output and abnormal loss may require additional configuration, reporting or accounting design.

For more information, see the official ERPNext Manufacturing documentation, Bill of Materials, Work Order and Job Card guides.

10. Reports and Cost Controls to Monitor

Calculating manufacturing cost once is not enough. Businesses should monitor the factors that cause the cost to change from one batch or production period to another.

1. Planned vs Actual Material Consumption

Shows whether production consumes more or less material than the BOM requires.

2. Material Price Variance

Highlights differences between expected material rates and actual purchase or valuation rates.

3. Labour Time and Cost Variance

Compares standard operation time with actual Job Card time and identifies activities taking longer than planned.

4. Machine and Production Overhead Report

Shows the overhead assigned to production using the selected allocation basis.

5. Wastage and Rejection Report

Tracks material loss, defective output, scrap and process yield by Item, batch or production operation.

6. Production Cost Per Good Unit

Combines the appropriate production costs and divides them by good finished output.

7. Product Profitability Report

Compares manufacturing cost with selling price and helps management review product margins.

Management QuestionUseful Metric
Are we consuming more materials than planned?Material usage variance
Are production employees taking longer than expected?Actual vs planned labour hours
Are machines operating efficiently?Machine hours and overhead per unit
How much material is lost during production?Wastage rate and process yield
How much does one saleable unit cost?Actual manufacturing cost per good unit
Are products meeting margin targets?Gross margin by Item or product family
Are costs increasing over time?Cost trend by batch and production period

11. Common Manufacturing Costing Mistakes

1. Calculating cost using raw materials alone

Ignoring labour, machine time and production overheads understates the actual cost of manufacturing.

2. Dividing by planned output instead of good output

If a batch is planned for 100 units but only 90 good units are completed, using 100 as the denominator may understate the cost per saleable unit. The business should also investigate whether the shortfall represents normal or abnormal production loss.

3. Ignoring material wastage

Cutting loss, process loss and other expected wastage can increase the material required for each good unit. These losses should be measured and reflected appropriately in production costing.

4. Treating abnormal waste as normal production cost

Unusual material loss, avoidable damage and abnormal production inefficiencies should be identified separately. Under IAS 2, abnormal wasted materials, labour and other production costs are excluded from inventory cost.

5. Using outdated Bills of Materials

An outdated BOM can cause incorrect material requirements, purchasing quantities and planned production costs. BOM revisions should be controlled and approved.

6. Using salary instead of an appropriate hourly labour rate

A monthly salary divided by calendar hours may not represent the cost of productive labour. The calculation should use a consistent and supportable productive-hour basis.

7. Allocating all overhead equally

Different products may use different machines, production hours and labour resources. A single overhead rate may distort the cost of products that consume resources differently.

8. Ignoring low production capacity

Fixed overhead allocation should consider normal capacity. Allocating all fixed overhead across an unusually small production quantity may overstate inventory cost.

9. Not recording actual production time

If actual labour and machine hours are not recorded, the business may rely on estimates indefinitely and miss opportunities to improve production efficiency.

10. Confusing manufacturing cost with selling price

Manufacturing cost is only one input into pricing. Distribution, sales, administration, financing, warranty and profit requirements may also need to be considered.

12. A Practical Manufacturing Costing Checklist

Product and material data

  • Maintain an approved Bill of Materials for each manufactured Item.
  • Keep material quantities and units of measure accurate.
  • Review material valuation rates regularly.
  • Document normal wastage assumptions.
  • Record actual material consumption.

Labour and operations

  • Define the operations required for each product.
  • Set realistic standard operation times.
  • Calculate loaded hourly labour rates consistently.
  • Capture actual labour time through an approved process.
  • Review rework and production delays.

Overheads and production capacity

  • Identify relevant fixed and variable production overheads.
  • Select an appropriate overhead allocation basis.
  • Establish normal production capacity.
  • Review machine utilisation and maintenance costs.
  • Keep production and non-production expenses separate.

Cost review and ERP controls

  • Compare planned and actual production costs.
  • Review material, labour and overhead variances.
  • Track good output, scrap and process loss.
  • Calculate cost per saleable unit.
  • Review selling price and margin by product.
  • Validate ERP reports against actual production records.

Get Better Visibility into What Each Product Really Costs

Accurate manufacturing costing requires more than a material price list. It requires reliable Bills of Materials, actual material consumption, labour time, machine and production overheads, and a clear record of good output and wastage.

ERPNext connects manufacturing operations, inventory movements, Work Orders, Job Cards and production costing records. With the right implementation and reporting design, manufacturers can compare planned costs with actual results and make better decisions about pricing, production efficiency and product profitability.

Craft Interactive helps businesses assess their manufacturing processes, implement ERPNext and configure workflows around their production and costing requirements.

Explore our ERPNext implementation services, learn why businesses choose ERPNext, or contact Craft Interactive to discuss your manufacturing requirements.

Further Reading and Official References

This article provides general management and costing guidance, not a substitute for an entity-specific accounting policy. The treatment of normal and abnormal wastage, scrap, overhead allocation, inventory valuation and production variances should be reviewed with the company's accountant or qualified adviser. ERPNext functionality can vary by version and configuration; validate the costing workflow against the installed version before go-live.

Free consultation

Talk to a consultant

A certified consultant calls you back within one business day.

We only use your details to reply. Privacy

Frequently asked questions

What is the formula for manufacturing cost per unit?
The basic formula is total manufacturing cost divided by the number of good units produced. Total manufacturing cost generally includes direct materials, direct labour and allocated manufacturing overheads.
Does manufacturing cost include wastage?
Normal expected production wastage should be reflected in material requirements and the cost of good output. Abnormal waste should be identified separately and treated according to the applicable accounting framework. Under IAS 2, abnormal amounts of wasted materials, labour and other production costs are excluded from inventory cost.
How do you calculate labour cost per unit?
Calculate the applicable hourly labour rate and multiply it by the production hours required for the batch. Divide the resulting labour cost by the number of good units produced to calculate labour cost per unit.
What is included in manufacturing overhead?
Manufacturing overhead can include production-related factory utilities, equipment depreciation, maintenance, indirect labour, factory facilities and other costs that support production. The allocation method should reflect how production resources are consumed.
Should machine depreciation be included in manufacturing cost?
Production-related machine depreciation is generally part of fixed manufacturing overhead and is allocated systematically to production, subject to the applicable accounting framework and normal-capacity requirements.
How do you calculate cost per unit when some products are rejected?
Identify the total production costs, good output, rejected quantity and the reason for rejection. The cost per good unit should reflect the appropriate costs of producing saleable output. Normal and abnormal production losses should be distinguished rather than treating all rejected units identically.
What is the difference between standard cost and actual manufacturing cost?
Standard cost is a predetermined expected cost based on defined material, labour and overhead assumptions. Actual manufacturing cost reflects the costs recorded for the production activity. Comparing the two helps identify cost variances.
Can ERPNext calculate manufacturing cost?
ERPNext supports BOM costing, planned operation costs, actual operating costs from Job Cards and material consumption through stock transactions. A complete cost-per-saleable-unit report that combines all actual costs, overhead allocation and production losses may require additional configuration or reporting.
How does wastage affect product pricing?
Wastage increases the material required to produce each good unit. If it is not included in the cost calculation, the business may quote a selling price that does not recover the actual production cost.
How often should manufacturing costs be reviewed?
Review frequency depends on production volume, material price volatility, process changes and business requirements. Costs should be reviewed when BOMs, supplier prices, labour rates, production methods or overhead allocation assumptions change. Actual batch results should also be monitored.
Is manufacturing cost per unit the same as total product cost?
Not necessarily. Manufacturing cost per unit covers production-related costs. A broader product profitability calculation may also include distribution, selling, administration, warranty and other costs that are not part of manufacturing inventory cost.

More articles

See what your business looks like when every team works from one system

A 45-minute ERPNext demo built around your own processes, run by a certified consultant.