Process map · Any company

Purchase to pay, step by step

Purchase to pay is everything between someone asking for an item and the supplier being paid for it. The money leaks in the gaps: orders nobody approved, deliveries nobody counted, invoices paid without checking them against either. In ERPNext each document is made from the one before it, so an invoice can only bill what was ordered and received.

Select a step to see who does it, the document and the ERPNext screen.

Step by step

  1. Whoever needs something raises a Material Request: the items, the quantity and the date they are needed by. Requests are also raised by the system when stock falls to an item's reorder level, and can be raised from a sales order that stock cannot cover.

    Who does it
    Storekeeper or any department
    Document that comes out
    Material Request

    ERPNext then does this by itself

    • Purchasing sees every open request in one list
    • The request shows how much has been ordered and received so far

    Without an ERP

    Requests arrive by phone, chat and a note on the buyer's desk. One is forgotten, another is ordered twice, and the store learns an item has run out when a customer asks for it.

    ERPNext 16: Submitted purchase material request with five electrical items, required-by date 23-11-2026, quantities and target warehouse
    ERPNext 16 · Material Request
  2. The Purchase Order is made from the chosen quotation, or straight from the request, so items, prices and terms carry over. It is emailed to the supplier as a PDF with the delivery date and the payment terms.

    Who does it
    Buyer
    Document that comes out
    Purchase Order

    ERPNext then does this by itself

    • The store sees what is due to arrive and when
    • The order tracks how much is received and billed
    • Quantities on order show in the stock reports

    Without an ERP

    Orders are placed by phone. When the goods and the invoice arrive, nobody can prove what price or quantity was agreed.

    ERPNext 16: Submitted purchase order to Al Dhafra Cables & Wires LLC, status To Receive and Bill, five items with rates, amounts and the tax table
    ERPNext 16 · Purchase Order
  3. When the goods arrive, the storekeeper opens the order and records what actually came, as a Purchase Receipt. A short or over delivery shows at once, because the receipt is made from the order.

    Who does it
    Storekeeper
    Document that comes out
    Purchase Receipt

    ERPNext then does this by itself

    • Stock goes up the moment the receipt is submitted
    • The value of the goods is posted to the accounts
    • The order is marked part or fully received

    Without an ERP

    The driver's delivery note is signed without counting. The shortage is found weeks later, after the supplier has been paid in full.

    ERPNext 16: Completed purchase receipt from Lumina Electrical Supplies FZE with seven items, accepted quantities, rates and accepted warehouse
    ERPNext 16 · Purchase Receipt
  4. The supplier's invoice is entered as a Purchase Invoice made from the receipt. This is the three-way match: the order says what was agreed, the receipt says what came, and the invoice may only bill for that.

    Who does it
    Accountant
    Document that comes out
    Purchase Invoice

    ERPNext then does this by itself

    • Billing more than was ordered or received is blocked
    • Ledger entries for the cost, VAT and payables are posted
    • The due date is set from the supplier's payment terms

    Without an ERP

    The invoice is paid as it arrives. It bills for 100 when 90 were delivered, at a higher price than the order, and nobody puts the three papers side by side.

    ERPNext 16: Submitted unpaid purchase invoice from Lumina Electrical Supplies FZE with supplier invoice number and date, due date and item lines
    ERPNext 16 · Purchase Invoice
  5. On payment day accounts open the payables report, see which invoices are due and pay them together. Each Payment Entry is recorded against the invoices it covers, and advances already paid to the supplier are taken off.

    Who does it
    Accountant
    Document that comes out
    Payment Entry

    ERPNext then does this by itself

    • Invoices are marked paid or part paid
    • Bank and payables ledgers are posted
    • The supplier's balance updates at once

    Without an ERP

    Payments go to whoever calls loudest. A supplier who offers a discount for early payment is paid late, and one invoice is paid twice from two different emails.

    ERPNext 16: Submitted supplier payment of AED 81,025 to Shenzhen Brightway Lighting by wire transfer, allocated against a purchase invoice
    ERPNext 16 · Payment Entry (Pay)

The Full map adds 8 more steps: the approvals, checks and branches between these.

For example
The store asks for 50 safety helmets. The buyer orders them from the supplier with the best quotation, 48 arrive, and accounts pay for 48.

Where this map leads

Processes feed each other. Follow the work into the next map.

Free tool

Build your company's map

Pick your industry and the processes you run. Get one printable document with every map and step, ready to show your team or your ERP partner.

See it live in a demo
  • Purchase to pay
  • Order to cash
  • Plan to produce
  • Project to bill
  • Patient to payment

Questions about purchase to pay

Ask us anything else
What is the purchase to pay process?
Purchase to pay (often written P2P, or procure to pay) is the full journey of a purchase: the request, the approval, the quotations, the purchase order, the goods receipt, the supplier's invoice and the payment. It ends when the supplier is paid and their statement agrees with your books.
What is a three-way match?
It is the check that a supplier's invoice agrees with two other documents: the purchase order, which says what was agreed, and the goods receipt, which says what arrived. In ERPNext the invoice is made from the receipt, which was made from the order, so the match is built in.
Which ERPNext documents make up purchase to pay?
Material Request, Request for Quotation, Supplier Quotation, Purchase Order, Purchase Receipt, Purchase Invoice and Payment Entry. A small company can skip the quotation steps and still keep the order, receipt and invoice linked.
Can we raise a purchase order without a request or quotations?
Yes. A Purchase Order can be raised directly, and the request and quotation steps skipped for small or urgent purchases. An approval workflow can be set up so that orders above an amount you choose still need a second person.
Can we pay a supplier before the goods arrive?
Yes. An advance is recorded as a Payment Entry against the purchase order. When the supplier's invoice is entered later, the advance is set against it, so only the balance shows as owed.

See this process run on your own data

A 45-minute ERPNext demo that follows this map with an example from your business.