Process map · Manufacturing

Purchase to pay in a manufacturing company

A factory does not buy because a shelf looks empty. It buys because the production plan says what will be made, the bills of materials say what that takes, and the store says what is already there. This map follows raw materials from the plan to the supplier's payment, with the two things a factory adds: incoming inspection and subcontracting.

Select a step to see who does it, the document and the ERPNext screen.

Step by step

  1. The planner pulls the sales orders to be made into a Production Plan. ERPNext works out the raw materials from the bills of materials, compares them with stock, and raises Material Requests for what is short. The plan is the approval.

    Who does it
    Production planner
    Document that comes out
    Material Request

    ERPNext then does this by itself

    • Quantities come from the bills of materials
    • Stock on hand and on order is taken off first

    Without an ERP

    The buyer orders from a planner's spreadsheet that missed one component. A whole production line waits three days for a box of fasteners.

    ERPNext 16: Submitted production plan pulling one sales order, with three assembly items, BOMs, planned quantities and start dates
    ERPNext 16 · Production Plan
  2. The order is made from the request, with the date the line needs the material. For a subcontracted job the order is for the supplier's service, and it names the finished item you expect back.

    Who does it
    Buyer
    Document that comes out
    Purchase Order

    ERPNext then does this by itself

    • The store and the planner see what arrives when
    • Material on order is counted in the next plan
    • The order tracks how much is received and billed

    Without an ERP

    The supplier ships when it suits them, because the order never said when the material was needed. The work order starts late, and so does the customer's delivery.

    ERPNext 16: Submitted purchase order to Al Dhafra Cables & Wires LLC, status To Receive and Bill, five items with rates, amounts and the tax table
    ERPNext 16 · Purchase Order
  3. Raw materials are received against the order into the store. A subcontracted job comes back on a Subcontracting Receipt, which takes in the finished item and uses up the materials you had sent.

    Who does it
    Storekeeper
    Document that comes out
    Purchase Receipt

    ERPNext then does this by itself

    • Stock goes up the moment the receipt is submitted
    • For outside work, the materials you sent are used up
    • The finished item is valued at materials plus the service

    Without an ERP

    The driver's delivery note is signed without counting. The shortage is found weeks later, after the supplier has been paid in full.

    ERPNext 16: Completed purchase receipt from Lumina Electrical Supplies FZE with seven items, accepted quantities, rates and accepted warehouse
    ERPNext 16 · Purchase Receipt
  4. The supplier's invoice is entered as a Purchase Invoice made from the receipt. This is the three-way match: the order says what was agreed, the receipt says what came, and the invoice may only bill for that.

    Who does it
    Accountant
    Document that comes out
    Purchase Invoice

    ERPNext then does this by itself

    • Billing more than was ordered or received is blocked
    • Ledger entries for the cost, VAT and payables are posted
    • The due date is set from the supplier's payment terms

    Without an ERP

    The invoice is paid as it arrives. It bills for 100 when 90 were delivered, at a higher price than the order, and nobody puts the three papers side by side.

    ERPNext 16: Submitted unpaid purchase invoice from Lumina Electrical Supplies FZE with supplier invoice number and date, due date and item lines
    ERPNext 16 · Purchase Invoice
  5. On payment day accounts open the payables report, see which invoices are due and pay them together. Each Payment Entry is recorded against the invoices it covers, and advances already paid to the supplier are taken off.

    Who does it
    Accountant
    Document that comes out
    Payment Entry

    ERPNext then does this by itself

    • Invoices are marked paid or part paid
    • Bank and payables ledgers are posted
    • The supplier's balance updates at once

    Without an ERP

    Payments go to whoever calls loudest. A supplier who offers a discount for early payment is paid late, and one invoice is paid twice from two different emails.

    ERPNext 16: Submitted supplier payment of AED 81,025 to Shenzhen Brightway Lighting by wire transfer, allocated against a purchase invoice
    ERPNext 16 · Payment Entry (Pay)

The Full map adds 10 more steps: the approvals, checks and branches between these.

For example
Next month's plan needs 2 tonnes of steel sheet and half a tonne is in the store. The plan raises a request for the rest, the sheets are inspected on arrival, and the cut parts go to a coating supplier and come back as finished stock.

What changes in a manufacturing company. The same process, the steps this industry really uses.

  • The plan decides what to buy

    The Production Plan works through every bill of materials, takes off what is in stock and on order, and raises Material Requests only for the shortfall.

  • Nothing reaches the line uninspected

    Items can be marked as needing inspection when bought. Their receipt cannot be completed until a Quality Inspection is recorded.

  • Some of the work is done outside

    When a supplier processes your materials, a Subcontracting Order tracks what you sent, what came back and what the service cost.

  • The date matters as much as the price

    Every request carries the date production needs the material, because one late component stops a whole work order.

Where this map leads

Processes feed each other. Follow the work into the next map.

Free tool

Build your company's map

Pick your industry and the processes you run. Get one printable document with every map and step, ready to show your team or your ERP partner.

See it live in a demo
  • Purchase to pay
  • Order to cash
  • Plan to produce
  • Hire to retire
  • Inventory management

Questions about purchase to pay

Ask us anything else
How does ERPNext know which raw materials to buy?
A Production Plan takes the sales orders you choose, reads the bill of materials of each item and adds up the raw materials. It compares the total with stock and raises Material Requests for the shortfall.
How does subcontracting work in ERPNext?
You raise a purchase order for the supplier's service and a Subcontracting Order from it. The materials you supply are transferred to the supplier's warehouse, and a Subcontracting Receipt brings the finished item back and uses those materials up. The item's cost is the materials plus the service.
Can we stop uninspected material from being used?
Yes. Mark the item as needing inspection before purchase, and its Purchase Receipt cannot be submitted without a Quality Inspection. Rejected quantities are received into a separate warehouse, apart from usable stock.